A week ago, on 28 April 2023, the President finally published, in the Government Gazette, his decision
to bring Section 6 of the National Energy Act (NEA), into operation. A couple of days before that The
Green Connection and the Southern African Faith Communities Environment Institute (SAFCEI)
received correspondence from the State Attorney on behalf of the President and the Minister in the
Department of Mineral Resources and Energy (DMRE), that the President had decided to bring Section
6 into operation with effect from 1 April 2024.
This follows more than two (2) years of unsuccessful correspondence with the President and Ministry
of Mineral Resources and Energy, in which The Green Connection and SAFCEI urged the President to
bring Section 6 into operation. The goal of that engagement was to progress and develop a proper
Integrated Energy Plan (IEP) in compliance with Section 6, for the country. As a result of the
unsuccessful engagement, after the President still hadn’t taken action, The Green Connection and
SAFCEI launched legal proceedings in January 2023 to review the President’s failure or refusal to bring
Section 6 of the NEA into operation.
The environmental justice organisations say, “While we have achieved, to some degree, what we had
set out to do – that is, for the President to agree to bring into operation the relevant Section of the
NEA that drives energy planning – the fact that it will only be effective from 1 April 2024, means that
only half the battle is won. In the midst of a crippling energy crisis, the President’s decision to wait a
year, leaves us with many questions and reservations, because it means that only then will the
Minister of the DMRE be legally required to get the ball rolling to start developing an IEP.”
What makes section 6 of the National Energy Act so important, is that it requires the Minister of
Mineral Resources and Energy to develop an Integrated Energy Plan (IEP), with public input, that
considers all the variables and influences, such as climate change and South Africa’s development
plans, and to review it annually. The IEP will serve as a guide for proposed energy projects, which
should be based on need and desirability and, if brought into effect, section 6 would curb disparate
decisions about South Africa’s energy future. According to the eco-justice organisations, there are a
host of energy projects – from oil and gas to nuclear – that are being considered and undertaken
without a comprehensive and long-term plan. The IEP is in the Energy Act because it balances
competing economic, environmental, political and social interests and sets the correct context in
which energy-related decisions are to be made. Most importantly, Section 6 guarantees an energy
plan that is developed in consultation with the people.
The Green Connection’s Advocacy Officer Kholwani Simelane says, “As South Africa limps through the
energy crisis, it is very confusing why the President would delay the process to start proper energy
planning – and in essence, extend the people’s suffering – by another year. What is the point of all
these ad hoc energy committees and task groups, if they cannot work together to get the country
geared towards integrated energy planning? If this is not the purpose of these measures, then it is just
another massive waste of public funds, which should be used to find real, tangible ways of dealing
with the crises. It is very difficult to understand why there are now further delays because we are living
in an electricity crisis right now. People are suffering now.”
“The President and Ministry have repeated the same excuses from when we first started writing to
them in November 2020, which are that various sector plans, which are not a prerequisite for enacting
Section 6, first need to be adopted. The question is, during a severe energy crisis, are these sector
plans – which may become null and void, as the integrated energy plan is developed – a valid reason
for the President to delay real action on energy planning? Can South Africans really afford to wait
another year before our government even starts to think about developing a proper energy plan?
South Africans should question whether these decisions are being driven by the needs of the people
or whether they are politically motivated. Additionally, many of these sector plans have already taken
several years to develop and are still incomplete.”
SAFCEI’s Executive Director, Francesca de Gasparis says, “It is good news that the President has
capitulated and that he has already made public his intention to bring Section 6 into operation, but 1
April 2024 to start the IEP process in terms of Section 6 seems to be kicking the can as far down the
road as possible. And we have not seen real commitment from the government to do what is needed
for the energy crisis to be addressed. The situation is incredibly urgent, South Africa is facing a long
cold winter with power cuts over 6 hours per day at present. Why does the government need so much
time to start the overarching plan for energy? Why plan for the IEP for next April 2024 when the energy
crisis should be their top priority? This is not even the bare minimum of what is needed. Government
must act faster!”
She says, “South Africa needs an urgent resolution to the energy crises now (not next year) with all
the mess that has been created as the result of doing energy projects without an energy
plan. Nonetheless, after 15 years since the National Energy Act (NEA) was first assented to in 2008
there is finally some movement. And we did not have to go all the way to court.”
The Green Connection and SAFCEI say they believe in dialogue and finding constructive solutions for
the greater good and, therefore, remain open to meaningful engagement with government on this
issue. And while the eco-justice organisations are happy that there is some movement toward realising
an Integrated Energy Plan (IEP), they continue to urge South Africans to question government’s motive
for the additional delay in bringing Section 6 into operation, and thus slow-walking the development
of the IEP. South Africans should ask their MPs and representatives about the IEP to make sure their
views are being heard in Parliament

BENDING OVER BACKWARDS, DMRE GIVES KARPOWERSHIPS ANOTHER BREAK
30 September 2021 was supposed to be the commercial close – a date set by the Department of Mineral Resources and Energy (DMRE) – for bidders in the Risk Mitigation Independent Power Producers Procurement Programme (RMI4P).

TOSACO EIA MET WITH PUSHBACK FROM CIVIL SOCIETY, TO PROTECT THE OCEAN AND SMALL-SCALE FISHER LIVELIHOODS
This week, The Green Connection submitted its comments critiquing several aspects of the Environmental Impact Assessment (EIA) process, particularly the lack of procedural fairness, as well as the conclusions reached – notwithstanding information gaps and scientific uncertainty – that should form part Tosaco Energy’s request to undertake various activities in Block 1, off the West Coast.

RECENTLY GRADUATED GREEN CONNECTORS, EQUIPPED FOR THE POLLS AND READY TO WEIGH-IN ON COP26
Following their recent graduation from The Green Connection’s Legacy Champions Programme, these newly empowered Green Connectors say they feel equipped with the necessary advocacy skills to make positive changes in their communities, starting with their vote in the local elections (1 November) and weighing in on the discussions around COP26 (which starts on 31 October) – as part of their efforts to oppose oil and gas developments in the country and offshore.

GREEN CONNECTION’S ‘FUNERAL FOR THE CLIMATE’ (AFRICAN ENERGY WEEK) AND COMMENT ON YESTERDAY’S BUDGET SPEECH
This week (10 November 2021), we joined other environmental defenders in Cape Town to peacefully demonstrate outside the African Energy Week #AEW2021 conference venue demanding an end to fossil fuels and the immediate pivot toward the just transition to a renewable energy future.

CLOSE TO 200 PEOPLE RISE AT CRACK OF DAWN TO PROTEST THE ARRIVAL OF SHELL’S SEISMIC MONSTER, AMAZON WARRIOR
On Sunday morning, (21 November 2021), before the crack of dawn, nearly 200 concerned environmental defenders took to the Waterfront to get a glimpse of Shell’s seismic testing vessel, Amazon Warrior, as it made its way into Cape Town harbour. The vessel travelled down the West coast of Africa, on its way to the Wild Coast, to conduct seismic surveys for an estimated five (5) months.

ENVIRONMENTALISTS DOUBLE-UP ON EFFORTS TO OPPOSE UPCOMING AND FURTHER SEISMIC TESTING IN SOUTH AFRICA’S OCEANS
As the groundswell of opposition against Shell’s upcoming 3D seismic survey off the Transkei builds, the Green Connection – an ecojustice NGO that supports small-scale fishers in advocating for their livelihoods – reacted with astonishment to a press statement issued by the Department of Mineral Resources and Energy (DMRE) on 9 December 2021.