The Green Connection says the Minister of Environmental Affairs Barbara Creecy made the right decision to decline Karpowerships’ appeal application against its failure to get environmental authorisations to operate in Saldanha Bay, Coega and Richards Bay. The eco-justice organisation says that at least, in the midst of another rather depressing Women’s Month, the fisherwomen – who were legitimately concerned about the negative impacts these ships would have on the ocean – have been vindicated in their fight to protect their livelihoods.
Earlier this month, The Green Connection received correspondence from DFFE confirming that Karpowerships had failed in its appeal to the Department of Forestry, Fisheries and Environment (DFFE). The Turkish company, which planned to supply additional power to South Africa via these floating kettles, was unable to overturn an earlier environmental ruling against its plans.
According to The Green Connection’s Strategic Lead Liziwe McDaid, the Minister’s decision comes to an overwhelming conclusion that “these gaps in information and the procedural defects are material and fatal and cannot be cured during the current appeal process”.
“In our view the Minister’s decision to uphold her department’s rejection of the Karpowership project is totally correct. However, her decision to then refer the matter back to the competent authority seems lame and sounds like a cop-out. Reading the detailed and damning appeal decision, we feel that it would be more appropriate for Karpowership to be directed to start at the very beginning, and it begs the question why the Minister has not said so?” says McDaid.
The Green Connection’s Community Outreach Coordinator Neville van Rooy says, “The Minister’s decision vindicates the small-scale fishers who were not properly consulted. We also expressed the importance of the need to do an underwater noise study to assess the impact of the Karpowership project on the fish on which small-scale fisher livelihoods depend.
“Another important point made in the appeal decision is that no so-called development project decisions, made by any arm of government, can trample over environmental rights. The flaws of this Environmental Impact Assessment are many and laid out for all to read,” adds van Rooy.
Fisherwoman with Coastal Links Saldanha Bay Carmelita Mostert says, “We are happy with the decision. Finally, some good news for women on the coast. It gives us hope and relieves a lot of stress that our oceans and marine life will be protected and that we can continue to provide for our children and our communities from the harvest of the sea.”
Fisherwoman, Solene Smith, also from Coastal Links in Langebaan, agreed with the Minister’s decision. She says, “We have said from the beginning that the Karpowership project will have a disastrous impact on our oceans and the dangers it poses could quite literally mean the end of our communities. We urge the government to look for greener, sustainable power solutions instead.”
Natalie-Jane van Wyk, a youth representative of Coastal Links Saldanha says, “The decision is a huge victory. We consider this development a huge win for us because the protection of the environment is fundamental to the existence of our communities. We will continue to stand together to fight against oil and gas companies who threaten our environment. We urge the government to embark on projects that protect and restore key eco-systems in our area.”
Vuyiseka Mani from the Eastern Cape Environmental Network (ECEN) says, “We are very happy with the decision, especially since we were not informed or invited to the public participation meeting regarding the Karpowership project. We will continue to fight for our voices to be heard. We won’t stop picketing, and we won’t stop petitioning and demonstrating. We will keep fighting for our rights, until the government takes our concerns about the environment seriously, instead of forcing projects on us which could damage the oceans and our communities.”

BENDING OVER BACKWARDS, DMRE GIVES KARPOWERSHIPS ANOTHER BREAK
30 September 2021 was supposed to be the commercial close – a date set by the Department of Mineral Resources and Energy (DMRE) – for bidders in the Risk Mitigation Independent Power Producers Procurement Programme (RMI4P).

TOSACO EIA MET WITH PUSHBACK FROM CIVIL SOCIETY, TO PROTECT THE OCEAN AND SMALL-SCALE FISHER LIVELIHOODS
This week, The Green Connection submitted its comments critiquing several aspects of the Environmental Impact Assessment (EIA) process, particularly the lack of procedural fairness, as well as the conclusions reached – notwithstanding information gaps and scientific uncertainty – that should form part Tosaco Energy’s request to undertake various activities in Block 1, off the West Coast.

RECENTLY GRADUATED GREEN CONNECTORS, EQUIPPED FOR THE POLLS AND READY TO WEIGH-IN ON COP26
Following their recent graduation from The Green Connection’s Legacy Champions Programme, these newly empowered Green Connectors say they feel equipped with the necessary advocacy skills to make positive changes in their communities, starting with their vote in the local elections (1 November) and weighing in on the discussions around COP26 (which starts on 31 October) – as part of their efforts to oppose oil and gas developments in the country and offshore.

GREEN CONNECTION’S ‘FUNERAL FOR THE CLIMATE’ (AFRICAN ENERGY WEEK) AND COMMENT ON YESTERDAY’S BUDGET SPEECH
This week (10 November 2021), we joined other environmental defenders in Cape Town to peacefully demonstrate outside the African Energy Week #AEW2021 conference venue demanding an end to fossil fuels and the immediate pivot toward the just transition to a renewable energy future.

CLOSE TO 200 PEOPLE RISE AT CRACK OF DAWN TO PROTEST THE ARRIVAL OF SHELL’S SEISMIC MONSTER, AMAZON WARRIOR
On Sunday morning, (21 November 2021), before the crack of dawn, nearly 200 concerned environmental defenders took to the Waterfront to get a glimpse of Shell’s seismic testing vessel, Amazon Warrior, as it made its way into Cape Town harbour. The vessel travelled down the West coast of Africa, on its way to the Wild Coast, to conduct seismic surveys for an estimated five (5) months.

ENVIRONMENTALISTS DOUBLE-UP ON EFFORTS TO OPPOSE UPCOMING AND FURTHER SEISMIC TESTING IN SOUTH AFRICA’S OCEANS
As the groundswell of opposition against Shell’s upcoming 3D seismic survey off the Transkei builds, the Green Connection – an ecojustice NGO that supports small-scale fishers in advocating for their livelihoods – reacted with astonishment to a press statement issued by the Department of Mineral Resources and Energy (DMRE) on 9 December 2021.